1, the hydraulic system pressure should comply with the instructions for use, and shall not be adjusted. Hydraulic oil and fuel oil should comply with the original requirements.
2, before loading concrete mixer truck, you should drain the remaining water and mix barrel debris. During transport to keep the rotation, to prevent concrete segregation. Before concrete mixer truck access to the site and unloading, should make full mixing drum to 14-18 rev / min rotation for 1-2 minutes, then invert discharge. Before reversing, should be parked mixing tube does not turn.
3, the ambient temperature is above +25 degrees Celsius, from the loading, transport, the discharge duration shall be more than 60 minutes, the ambient temperature is below +25 degrees Celsius, the above time shall not exceed 90 minutes.
4, winter construction machinery, should earnestly: before starting the check for icing; work when the barrel and mix carefully exclude residual water supply system, turn off the pump switch, the control lever in the "stop" position.